ROOF DRIP SIDE FINISH MOULDING > INSTALLATION

for Preparation Click here


HINT:
  1. Use the same procedures for the RH side and LH side.
  2. The procedures listed below are for the LH side.
  3. When replacing the clip, heat the clip and body using a heat light.

    Standard:
    Item
    Temperature
    Vehicle body
    40 to 60°C (104 to 140°F)
    Clip
    20 to 30°C (68 to 86°F)

NOTICE:
Do not heat the clip and vehicle body excessively.


1. REPLACE ROOF DRIP SIDE FINISH MOULDING CLIP

HINT:
Use the procedures below to replace damaged or accidentally removed clips. If this step is not necessary, go to the next step.

NOTICE:
After press-fitting the clips, wait 30 minutes or more before installing the moulding.

HINT:
  1. Minimum hardening time: 30 minutes
  2. Time needed for complete hardening: 24 hours
  1. Remove the double-sided tape that remains on the surfaces of the moulding and vehicle body, and then clean the surface with white gasoline.

  1. Using a heat light, heat the clip installation surface of the vehicle body and installation part of the clips.



2. INSTALL ROOF DRIP SIDE FINISH MOULDING LH


B127947
  1. Install the No. 2 center roof drip side finish moulding and roof drip side finish moulding.

  1. Install the 2 roof drip moulding joint covers to the vehicle body.